When this report was published on November 27, 2026, at 01:10:03 UTC+8, CleanSpark had collected $5 million from the technology tenant leasing its Sandersville, Georgia, data center. The company booked the payment as an advance against rent, not as earned income. Its November 24 annual filing, as reported by Crypto.news, showed no lease revenue for the fiscal year ended September 30.
The lease provides for about $6.56 billion in base rent over 20 years, excluding variable reimbursements and optional extensions. But contracted rent is not cash CleanSpark can use to pay its bills now. Until the data halls begin service, the company still relies on Bitcoin production and its treasury to fund operations.
When the debt and rent payments begin
CleanSpark financed the project with $2.276 billion in CSDC Finance I notes. The notes carry a 7.875% coupon, settle at 98.5% of par and mature in 2031. The payment schedules differ:
- April 1, 2027: The first interest payment is due.
- November 2027 to March 2028: The lease is expected to start in phases as CleanSpark delivers data halls covering 175 megawatts of critical IT load. The first hall is expected about seven months after the first interest payment.
- October 1, 2028: Principal installments are expected to begin under the current timetable.
About $2.14 billion of CleanSpark’s fiscal year-end cash was restricted to Sandersville development, alongside a $327 million debt service reserve. The notes restrict transfers out of the project entities. Once rent starts, it must cover project expenses and debt service before any money reaches the parent company.
The guarantees cover different obligations. CleanSpark must fund its project subsidiary if note proceeds and other committed funds fall short of construction costs. The tenant’s parent guarantees lease payments only up to a cap tied to unpaid base rent and operating expenses. CleanSpark also recorded a $177.1 million impairment, largely related to converting Sandersville from mining to data center use.
How Bitcoin funds operations in the meantime
Fiscal 2026 mining revenue fell to $576.5 million from $766.3 million a year earlier. Production declined from 7,873 BTC to 7,253 BTC, and average hashrate fell 21% to 36 exahashes per second. CleanSpark paid an average of 5.5 cents per kilowatt-hour at its owned sites; the energy cost per bitcoin mined rose to $47,130.
CleanSpark reported a $987.1 million net loss, compared with net income of $364.5 million in fiscal 2025. A $707.3 million swing in Bitcoin fair-value adjustments was a major contributor: a $425.6 million gain became a $281.6 million loss. By contrast, net cash used in operating activities rose only from about $461.0 million to $468.4 million. CleanSpark raised $609.2 million from Bitcoin sales and settlements of Bitcoin-linked derivatives, which it classified as investing activities rather than operating cash flows.
In the final quarter, CleanSpark mined 1,708 BTC and sold or delivered 2,102 BTC. Option exercises helped explain why deliveries exceeded output: in September, it delivered 700 BTC through call options and sold two coins on the spot market. Its reported year-end treasury of 13,530 BTC included a receivable for 1,810 BTC posted as collateral, so not all of that balance was available to sell.
On the November 24 earnings call, President and CFO Gary Vecchiarelli said CleanSpark intended to sell nearly all newly mined Bitcoin to cover operating expenses. He left open the possibility of modest sales beyond production. Ahead of the first data hall delivery, the company’s quarterly disclosures on coin sales, collateral receipts and revenue from tenant fit-out work will help distinguish cash available to the miner from funds committed to Sandersville.